FUSION DEVELOPERS · INITIAL CLIENT PROPOSAL

Venus Pharma

55 ft × 77 ft Pre-Engineered Building Shed
with Integrated 63.4 kWp Rooftop Solar PV System

PKR 11,135,234

Lahore, Pakistan · Reference FD-COMM-001 · 02 August 2026

4,235 sftCovered area
26 ft / 20 ftFront and back wall heights
63.4 kWpIntegrated rooftop solar
Single contractStructure, envelope, civil and solar

Executive Summary

Fusion Developers proposes a purpose-designed mono-slope PEB package bringing the steel structure, building envelope, foundations and rooftop solar EPC scope under one accountable delivery team. The current package is supported by coordinated design drawings, fabrication information, BOQ and 3D review material.

Proposed Scope

Commercial Summary

ScopeAmount (PKR)
PEB steel structure2,580,200
Roof and wall cladding1,222,440
Finishes / coating150,000
Solar PV equipment — 63.4 kWp4,146,000
Solar BOS / electrical835,500
Earthwork / foundations700,000
Preliminaries — labour and site488,800
Subcontract total10,122,940
Overhead & Profit @ 10%1,012,294

Total Contract Sum: PKR 11,135,234

Optional Enhancements

Battery Storage215 kWh LFP battery bank with hybrid PCS, subject to final load-profile review and separate quotation.
Solar-Optimized StructureEnhanced frame and purlin configuration at an indicative PKR 295/sft, subject to final engineering.

Next Steps

  1. Joint proposal and operational-requirements review.
  2. Freeze geometry, finishes, equipment basis and scope.
  3. Issue the formal quotation, milestones and baseline programme.
  4. Contract award, site handover and drawing release.

Initial proposal: Final taxes, payment milestones, programme, warranties, approvals, logistics and exclusions will be defined in the formal quotation and contract. Final engineering remains subject to verified site conditions and approved operational requirements.