FUSION DEVELOPERS · INITIAL QUOTATION PROPOSAL

Venus Pharma

55 ft × 80 ft Pre-Engineered Building Shed · 4,400 sft

PEB Structure · Solar-Optimized Frame · Civil Works

CEO Summary

Decision requested: approve the PKR 9,568,154 quoted base and confirm whether the optional approximately 64 kW solar package is required.

The recommended award basis combines the PKR 7,368,900 PEB package with PKR 2,199,254 of civil works. The PEB is structurally optimized for solar loading; installed solar remains separate at an indicative PKR 5,696,000 (PKR 89/W × approximately 64,000 W). Order confirmation releases 50% of the PEB value. All rates exclude GST and applicable taxes, and the stated exclusions should be confirmed before mobilization.

PKR 7,368,900PEB package
PKR 2,199,254Civil package
PKR 9,568,154Combined quoted base
64 kW optionalSolar at PKR 89/W

3D Project Views

PEB Structure Package

Quotation reference FD-INV-2026-001, dated 29 July 2026.

Description Rate Amount (PKR)
Roof + 25 mm glass wool + four-side PPGI 1,300/sft 5,720,000
Solar-optimized PEB shed add-on 295/sft 1,298,000
Construction subtotal 7,018,000
Company overhead @ 5% 350,900
PEB PACKAGE TOTAL: PKR 7,368,900

PEB Payment Schedule

Milestone Percentage Amount (PKR)
Order confirmation 50% 3,684,450
Material delivery 30% 2,210,670
PPGI / cladding installation 10% 736,890
Final completion 10% 736,890

Civil Works Package

Quotation reference FD-INV-2026-002, dated 01 August 2026. Scope covers twenty column foundations and a 9-inch perimeter brick wall of approximately 1,584 sft.

Description Amount (PKR)
Foundation works — 20 columns 1,254,420
9-inch perimeter brick wall — 1,584 sft 676,720
Measured subtotal 1,931,140
Carriage & miscellaneous 50,000
OH&P @ 10% 198,114
Design fee 20,000
CIVIL PACKAGE TOTAL: PKR 2,199,254

Optional Solar PV — Not Included

Approximately 64,000 W × PKR 89/W = PKR 5,696,000

The PEB quotation includes the solar-optimized structural add-on only. Solar modules, inverters, BOS, electrical interconnection, monitoring, regulatory approvals and installation are excluded from the quoted base and require final technical confirmation.

Scope Summary

Commercial Clarifications

Important: Quoted rates are exclusive of GST and applicable taxes. The PEB quotation excludes foundations, civil works, MEP, site preparation, transport and installed solar PV. The brick-wall quotation excludes its own PCC footing and DPC unless separately instructed. Final execution remains subject to approved drawings, site readiness and agreed logistics.