FUSION DEVELOPERS · INITIAL QUOTATION PROPOSAL

Venus Pharma

55 ft × 80 ft Pre-Engineered Building Shed · 4,400 sft

PEB Structure · Solar-Optimized Frame · Civil Works

PKR 7,368,900PEB package
PKR 2,199,254Civil package
PKR 9,568,154Combined quoted base
64 kW optionalSolar at PKR 89/W

PEB Structure Package

Quotation reference FD-INV-2026-001, dated 29 July 2026.

DescriptionRateAmount (PKR)
Roof + 25 mm glass wool + four-side PPGI1,300/sft5,720,000
Solar-optimized PEB shed add-on295/sft1,298,000
Construction subtotal7,018,000
Company overhead @ 5%350,900
PEB PACAGE TOTAL: PKR 7,368,900

PEB Payment Schedule

MilestonePercentageAmount (PKR)
Order confirmation50%3,684,450
Material delivery30%2,210,670
PPGI / cladding installation10%736,890
Final completion10%736,890

Civil Works Package

Quotation reference FD-INV-2026-002, dated 01 August 2026. Scope covers twenty column foundations and a 9-inch perimeter brick wall of approximately 1,584 sft.

DescriptionAmount (PKR)
Foundation works — 20 columns1,254,420
9-inch perimeter brick wall — 1,584 sft676,720
Measured subtotal1,931,140
Carriage & miscellaneous50,000
OH&P @ 10%198,114
Design fee20,000
CIVIL PACKAGE TOTAL: PKR 2,199,254

Optional Solar PV — Not Included

Approximately 64,000 W × PKR 89/W = PKR 5,696,000

The PEB quotation includes the solar-optimized structural add-on only. Solar modules, inverters, BOS, electrical interconnection, monitoring, regulatory approvals and installation are excluded from the quoted base and require final technical confirmation.

Scope Summary

Commercial Clarifications

Important: Quoted rates are exclusive of GST and applicable taxes. The PEB quotation excludes foundations, civil works, MEP, site preparation, transport and installed solar PV. The brick-wall quotation excludes its own PCC footing and DPC unless separately instructed. Final execution remains subject to approved drawings, site readiness and agreed logistics.