PKR 7,368,900PEB package
PKR 2,199,254Civil package
PKR 9,568,154Combined quoted base
64 kW optionalSolar at PKR 89/W
PEB Structure Package
Quotation reference FD-INV-2026-001, dated 29 July 2026.
| Description | Rate | Amount (PKR) |
|---|---|---|
| Roof + 25 mm glass wool + four-side PPGI | 1,300/sft | 5,720,000 |
| Solar-optimized PEB shed add-on | 295/sft | 1,298,000 |
| Construction subtotal | 7,018,000 | |
| Company overhead @ 5% | 350,900 |
PEB PACAGE TOTAL: PKR 7,368,900
PEB Payment Schedule
| Milestone | Percentage | Amount (PKR) |
|---|---|---|
| Order confirmation | 50% | 3,684,450 |
| Material delivery | 30% | 2,210,670 |
| PPGI / cladding installation | 10% | 736,890 |
| Final completion | 10% | 736,890 |
Civil Works Package
Quotation reference FD-INV-2026-002, dated 01 August 2026. Scope covers twenty column foundations and a 9-inch perimeter brick wall of approximately 1,584 sft.
| Description | Amount (PKR) |
|---|---|
| Foundation works — 20 columns | 1,254,420 |
| 9-inch perimeter brick wall — 1,584 sft | 676,720 |
| Measured subtotal | 1,931,140 |
| Carriage & miscellaneous | 50,000 |
| OH&P @ 10% | 198,114 |
| Design fee | 20,000 |
CIVIL PACKAGE TOTAL: PKR 2,199,254
Optional Solar PV — Not Included
Approximately 64,000 W × PKR 89/W = PKR 5,696,000
The PEB quotation includes the solar-optimized structural add-on only. Solar modules, inverters, BOS, electrical interconnection, monitoring, regulatory approvals and installation are excluded from the quoted base and require final technical confirmation.
Scope Summary
- 55 ft frontage × 80 ft depth
- Approximately 4,400 sft covered area
- Roof with 25 mm glass-wool insulation
- Four-side PPGI cladding
- Solar-optimized PEB structure
- Twenty column foundations
- 9-inch perimeter brick wall
- 80 no. 25 mm J-anchor bolts
Commercial Clarifications
Important: Quoted rates are exclusive of GST and applicable taxes. The PEB quotation excludes foundations, civil works, MEP, site preparation, transport and installed solar PV. The brick-wall quotation excludes its own PCC footing and DPC unless separately instructed. Final execution remains subject to approved drawings, site readiness and agreed logistics.